Difference Between The Role of Sponsor And Customer

The Customer

  • will pay for the project’s product. 
  • will give the products’ requirements and reap benefit from the product (usually long after the project is over). 
  • may or may not be part of the Performing Organization.

The Sponsor

  • is usually part of the Performing Organization. 
  • will decide how much funds will be used for the project. She/he will take budgetary decisions. 
  • will appoint the Project Manager and provide necessary support to her/him.

Comments

  1. Examples
    Let us consider 2 different projects that are done by a PO under a contract from an external CO.

    A project done for profit – The Client agrees to pay $100K for a fixed price project. The Sponsor from the PO decides to do the project for $80K and rest will be deemed as profit.

    A project done for a social cause – A Donor Agency (Client) initiates a disaster management project. It contracts an independent non-profit organization (PO) to meet project’s objectives. The Sponsor from the Donor Agency will take decisions about the project budget and disburse the funds as needed to manage the costs.

    ReplyDelete